Antea Polska S.A. has signed an agreement with Michelin Polska S.A. for design and consulting support in the construction of a new steam-gas boiler with a capacity of 42MWt in fuel.

The project is part of the Sage project, which consists in changing the existing coal boilers and replacing them with new gas units meeting the latest environmental requirements. This is the next stage of the investment, in which Antea Group is involved.

Scope of services

The scope of activities includes preparation of project documentation and obtaining a valid building permit on its basis together with the necessary prior agreements and permits required by law, as well as preparation of tender documentation (RFP EPC).
Antea will also be responsible for conducting the tender for the implementation of the investment in order to select the contractor and prepare the complete contract with the general contractor, taking into account the adopted schedules and the appropriate quality of the investment.